The Background
In 2024, Procter Contracts was commissioned by Cwm Taf Morgannwg Health Board to improve the safety of exposed hospital stairwells at a mental health unit. The stairwells posed several risks, including attempted suicides, unsafe surfaces in bad weather, and misuse as smoking areas.
The Health Board required a solution that would:
-
Prevent opportunities for self-harm or suicide attempts
-
Improve security and safety without impeding emergency exits
-
Remain independent of the existing building structure
-
Deliver within tight NHS timescales
The Challenge
The stairwell was a self-supporting, floating structure built on a concrete pad. Any new design had to avoid overstressing the foundations while still providing complete enclosure. Additionally, the exposed location meant surfaces were slippery and unsafe during poor weather, and the open design created opportunities for climbing or jumping.
The Health Board needed a contractor capable of handling the full package — design, structural calculations, manufacture, and installation — while ensuring compliance with NHS and external safety requirements.
The Solution
Procter Contracts engineered a bespoke screening system by extending the existing support frames and fitting modular perforated cladding with a powder-coated galvanised steel finish. The cladding and roof design eliminated climbing or falling risks, while its perforated pattern reduced wind loading and allowed natural light to enter the stairwells.
Key features of the solution included:
-
Independent structure to avoid impacting the existing building
-
Verified structural calculations and NHS contractor approvals
-
Emergency lighting and weather protection integrated into the design
-
Discreet cladding that minimised visual impact while providing security
The Result or Feedback
The new stairwell screening achieved all objectives, significantly improving safety while maintaining the structure’s emergency exit function. The installation was completed on time and within budget, to the full satisfaction of the Health Board.
John Procter, Managing Director at Procter Brothers, commented:
“This was a really interesting project where we brought together our design, manufacture, and installation expertise to deliver a single-source solution. The job went smoothly for both parties, and it was very satisfying to complete a project that will help keep people safe.”
Why Procter Contracts?
This project highlights our ability to deliver bespoke safety screening solutions and structural security works in sensitive environments. By combining in-house design, engineering, and installation, Procter Contracts provides clients with a single point of responsibility — ensuring cost-effective, compliant, and robust results.
Discover more of our expertise in fencing and security solutions, or see our award-winning Castle Park case study for another example of our work.
Products used